QUESTION 6 Consider a project that has the following activities, along with their duration estimates: Estimated Duration (Days) Task Predecessors None None 14 12 B,F, G C, H Which of the following statements are true for this project? [Multiple answers may apply] The activity sequence C-H-J is a critical path for this project.