This Question: 2 pts 11 of 33 (8 complete)This Test: 103 pts possible Question Help The Jacobs Ladder Company produces a ladder in an assembly line process that is represented by the given precedence chart. The daily available production time is 7 hours (eight-hour workday less 1 hour of setup and break time). The average daily demand is seventy (70) units Task Time Task Immediate Predecessor(s) (mins) 2 5 A, C 3 What is the cycle time for this assembly line in minutes per unit? OB. 0.1 OC, 6 O D. 70 Click to select your answerThis