QUESTION 19 15 points ( Now the moment you have been waiting for: AN EXTRA CREDIT OPPORTUNITY! We want to recommend reductions to the project time line for our boss. The network diagram currently has the following sequence and timing of activities. C(3)E(5)G(15) A(5) H(5) B(10) D(10) F(5) Which of the following