Question 1 Consider a process that consists of two steps: Milling and Assembly. There is unlimited space for buffer inventory

Question 1 Consider a process that consists of two steps: Milling and Assembly. There is unlimited space for buffer inventory between the two steps. The setup time for Milling is 120 minutes, and the activity time for each product at Milling is 2 minutes. There is no setup time at Assembly. The activity time for each product at Assembly is 3 Milling Assembly Is milling or assembly the bottleneck when the batch size of the process is