A project completion time can be assumed to berepresented by a normal distribution curve The project is expectedto complete in 36 weeks with a path variance of 6.67 Base on theinformation provided, calculate: a. Calculate the probability thatthe project will be completed in 39 weeks or less b. Theprobability that the project will be completed in between 33.5 and38 weeks c. With 95 percent probability, calculate the date theproject can be completed.
Expert Answer
A solution will be send to your mail shortly . . . .