Product A is made of 3 units of B and 2 units of C. Each B is made up of 2 units of D and 3 units of E. Each E is made of 3 units of F and 1 unit of G. C is made of 1 unit of D and 4 units of E. Lead times for all items are one week except for B. The lead time for B is 3 weeks. 100 units of A are needed at the start of week 9. There are currently 32 units of Bon hand, and 212 units of E