PROCESS ANALYTICS Applying the TOC methodology to processesallows you to determine the efficiency of processes and to makeimprovements to the system. Consider an operating system with 9activities and 3 resource types X, Y and Z. The first threeactivities, Activities 1, 2 and 3 require 10 minutes/unit each, andthe remaining activities require 5 minutes/unit each. Activities 1,2 and 3 require Resource X; Activities 4, 5 and 6 require ResourceY; and Activities 7, 8 and 9 require Resource Z. Each resource has2400 minutes of weekly processing time available. Different jobsneed a specific set of these activities and as expected, the jobshave varying