Course Solutions Uncategorized (Answered) : Problem 12-3 The following table lists the components needed to assemble an end item, lead times (in weeks). and quantities on han

(Answered) : Problem 12-3 The following table lists the components needed to assemble an end item, lead times (in weeks). and quantities on han

Problem 12-3 The following table lists the components needed to assemble an end item, lead times (in weeks). and quantities on hand. adAmount Tine on Hand Direct し(2)· 3(1), K(3) B(2), J(3) G (2), B(2) H(4), B(2) End 10 15 31 a. If 43 units of the end item are to be assembled. how many additional units of B are needed? (Hint You don’t need to develop an 516 0 b. An order for the end item is scheduled to be shipped at the start of week 8. What is the latest week that the order can be started and