Prepare a master schedule given this information: It is now theend of week 1; customer orders are 25 for week 2, 16 for week 3, 11for week 4, 8 for week 5, and 3 for week 6. Use the MPS rule ofordering production when projected on-hand inventory would benegative without production. Suppose that there are currently 64pumps in inventory and a production lot size of 70 pumps is used.(Leave no cells blank – be certain to enter “0” whereverrequired.)