Please answer: urgent. Solution there but can’t understand howto do it step by step
A large building company determined the need for cranes at threedifferent building sites (A, B, and C) for the next 6 weeks (seeTable 1). The demand for cranes is for full-time availabilityduring a particular week. At the moment (start of week 0), all thecranes are located at the company’s main depot.
|
Site |
Week 1 |
Week 2 |
Week 3 |
Week 4 |
Week 5 |
Week 6 |
|
A |
1 |
2 |
1 |
0 |
0 |
0 |
|
B |
0 |
1 |
2 |
2 |
1 |
1 |
|
C |
1 |
0 |
0 |
0 |
2 |
2 |
Table