Please answer quickly
Using the EDD (earliest due date) decision rule for sequencingthe jobs, the order is (to resolve a tie, use the order in whichthe jobs were received):
|
Sequence |
Job |
|
1 |
▼ E A C B D |
|
2 |
▼ E D B C A |
|
3 |
▼ E D C B A |
|
4 |
▼ A E C B D |
|
5 |
▼ A E B C D |
The total flow time for the sequence developed using the EDDrule =
nothing
days (round your response to two decimal places).Thepercentage utilization for the sequence developed using the EDDrule =
nothing%
(enter your response as a percentage rounded to two decimalplaces).The average number of jobs in the system for the sequencedeveloped using the EDD rule =
nothing
jobs (round your response to two decimal places).The averagetardiness (job lateness) for the sequence developed using the EDDrule =
nothing
days (round your response