The partially completed inventory record for the rotor subassembly in the table below shows gross requirements, scheduled receipts, lead time, and current on-hand inventory. Complete the last three rows of the record for an FOQ of 160 units. (Enter your responses as integers. A response of O is equivalent to being not applicable.) Item: Rotor subassembly Lot Size: FOQ-160 units Lead Time: 2 weeks Week 4 7 Gross requirements Scheduled receipts Projected on-hand inventory Planned receipts Planned order releases 30 70 70 70 70 160