Order cost=70
Unit cost=25
Holding cost =, 2 x 25 =5
Part C- Uncertain Demand RC:70 (HC>,2x 25 After one year of operations, the Nawras Electronics Company reached agreement with suppliers to ensure a constant lead time of 7 days. However, the company also realized that daily demand for laptops exhibited some variability, with the mean annual demand still at 3200 units, but with a standard deviation of 150 laptops. 6d 21. The company has decided on a service level of 95%. Accordingly, what size of safety stock should be kept to cope with uncertainty? policy type I service level is not enough