Jobs23456 P 001 .2 Using the rule JLNO-MIN。(job with largest number of operations first on the machine with the largest number of operations), find an optimal schedule.
https://media.cheggcdn.com/media%2Ff76%2Ff764c5a7-8524-4fc2-90f1-2a9695a798dd%2Fimage
Expert Answer
Ans: Following is the job schedule by following JLNO -MLNO rule.
Job 6 on machine 1,
Job 5 on machine 3
Job 3 on machine 2
Job 4 on machine 1
Job 2 on machine 3
Job 1 on machine 2