In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week. (Leave no cells blank – be certain to enter “0” wherever required.)
WEEK NUMBER
ITEM J 0 1 2 3 4 5
Gross requirements 70 45 65
On-hand 30
Net requirements
Planned order receipt
Planned order release
I NEED THIS BOTTOM CHART FILLED OUT NOT THE TOP CHART, THANK YOU
Period 1 2 3 4 5
Item