Course Solutions Uncategorized (Answered) : I Create a Network Diagram m. Calculate ES, EF, LS, LF (Early Start, Early Finish, Late Start, Late Finish) n. Define the Critical

(Answered) : I Create a Network Diagram m. Calculate ES, EF, LS, LF (Early Start, Early Finish, Late Start, Late Finish) n. Define the Critical

I Create a Network Diagram m. Calculate ES, EF, LS, LF (Early Start, Early Finish, Late Start, Late Finish) n. Define the Critical Path o. How many weeks will the project take to complete? Immediate ctivity Predecessor Time 4 C, D 4 E, F

https://d2vlcm61l7u1fs.cloudfront.net/media%2Ff98%2Ff98ac61e-1845-4dec-8eb6-9faa3d79ac3f%2FphpB9ogVg.png

Expert Answer


https://d2vlcm61l7u1fs.cloudfront.net/media%2Fac2%2Fac21fc01-8839-46ae-baf6-6869dd30fe06%2Fphp6k9NmI.png

https://d2vlcm61l7u1fs.cloudfront.net/media%2F58a%2F58a31f80-695e-4977-8baf-6900dabbc129%2FphpOnjxN5.png

m) The ES, EF, LS & LF are as calculated above in table.

n) The critical path is the longest path and consists of critical activities which have zero slack. So the critical path is B-D-E-G

o) The project will take 18 weeks to complete which is the EF or the LF as mentioned in