Given the following production information, complete the planned order releases and projected on-hand balances for component part X.
Part X Week1 Week 2 Week 3 Week 4 Week 5
Gross Requirements 80 50 60 50 90
Scheduled Receipts 120
Project Balance 100
Planned Order Release
Q = 40; LT = 3 weeks; Safety Stock = 10