Given the following data, develop MRP tables and indicate the Planned order releases for all items.

A is an MPS item. A needs 4 C’s and 2 F’s. Every C needs 6 F’s.

Period

6

7

8

9

GR-A

0

0

2000

1500

On hand inventory for all items is 400 and lead time for A is 1 period, LT for F is 1 period and LT for C is 2 periods. Use lot-for-lot for A and a lot size of 900 or multiples of 900 for C and lot size of 2000 or multiples of 2000 for F.

Draw the Bill of Material

OR

PayPal Gateway not configured

OR

PayPal Gateway not configured

Leave a Reply

Your email address will not be published. Required fields are marked *

Related Post

(Answered) : Identify at least two of the common problems that are associated with managing virtual teams. After identifying the problems, de(Answered) : Identify at least two of the common problems that are associated with managing virtual teams. After identifying the problems, de

Identify at least two of the common problems that are associated with managing virtual teams. After identifying the problems, describe a team-building method that could be applied to each situation.