Exercise 9: Consider the following project time data (in days) and the network diagram Activity A B C DEF G H Time10 10 12 8 6 10 6 12 3E(6) C(12) G(6) A(IO) H(12) Pummy D(8) B(10) F(10) 4 a) Find earliest and latest starting and finishing times and the slack values for all of the activities. b) Determine the critical path and the project completion time c) When will the project be completed if activity D takes 10 days to complete? If activity B takes 11 days to complete?
https://d2vlcm61l7u1fs.cloudfront.net/media%2F422%2F422cdb0e-b7ce-420e-ba23-7acf1b6dbacd%2FphpBMYAtt.png
Expert Answer
Earliest start (ES), Earliest Finish (EF), Latest