Eat fresh restaurant has four activities in serving a customer: The activities are listed below in the table. There is one worker performing each activity ctivity Processing time per customer 5 seconds 15 seconds 1 minute 2 seconds 8 Assume demand is unlimited. If the restaurant management were to add two additional workers to the bottleneck activity, what will be the percentage change in process capacity?