Eat fresh restaurant has four activities in serving a customer: The activities are listed below in the table. There is one worker performing each activity. Activity Processing time per customer 5 seconds 15 seconds 1 minute 2 seconds 1) Assume demand is unlimited. If the restaurant management were to add two additional workers to the bottleneck activity, what will be the percentage change in process capacity?

https://d2vlcm61l7u1fs.cloudfront.net/media%2F0f7%2F0f79920e-f30c-4d8d-906c-668ba5231c74%2FphpDW9Z0K.png

Expert Answer


Current capacity

When 2 additional workers is added to activity C, processing time will reduce to 20 secs

New Capacity= 3 customer per min

Hence Process capacity change =(3-1)/1*100=200%

Leave a Reply

Your email address will not be published. Required fields are marked *

Related Post

(Solved) : Eastwest Airline Company Wants Help Develop Program Generates Flight Itinerary Customer Re Q37505843 . . . .(Solved) : Eastwest Airline Company Wants Help Develop Program Generates Flight Itinerary Customer Re Q37505843 . . . .

C++//add comments<br/><img src="https://media.cheggcdn.com/media%2Ff8e%2Ff8e17a7e-13b1-433b-a9ab-9c63928105ec%2Fimage.png" alt="The EastWest airline company wants you to help them develop a program that generates flight itinerary for customer requests t" aria-describedby="d3f"/><img src="https://media.cheggcdn.com/media%2F461%2F461b12a7-162c-416c-ab47-1fb94e047e79%2Fimage.png" alt="301 AM Mon Apr 29