Eat fresh restaurant has four activities in serving a customer: The activities are listed below in the table. There is one worker performing each activity. Activity Processing time per customer 5 seconds 15 seconds 1 minute 2 seconds 1) Assume demand is unlimited. If the restaurant management were to add two additional workers to the bottleneck activity, what will be the percentage change in process capacity?
https://d2vlcm61l7u1fs.cloudfront.net/media%2F0f7%2F0f79920e-f30c-4d8d-906c-668ba5231c74%2FphpDW9Z0K.png
Expert Answer
Current capacity
When 2 additional workers is added to activity C, processing time will reduce to 20 secs
New Capacity= 3 customer per min
Hence Process capacity change =(3-1)/1*100=200%