Drawing of a Network 7A construction project with the following precedence relationships is being planned. Draw an activity-on-arrow diagram for the project. Number the nodes. Show a clean network. | (1) S is the last operation; P is the first operation. (2) M and L can both start in parallel after completion of P (3) H follows L (4) Both B and E can be done concurrently, but only after the finish of M. (5) B precedes O. (6) H precedes G (7) E must be finished before G starts. (8) A cannot start until both the completion of O