Consider the table of tasks, immediate predecessors and estimated task time below:
Activity
Immediate Predecessor
estimated task time
Slack
A
—
5
B
—
3
C
A
7
D
A
6
E
B
7
F
D, E
3
G
D, E
10
H
C, F
8
Draw the project diagram. Please try to keep it right-side up so that we can grade it easily. Use as much paper as you need, as long as the diagram is clear.
What is the critical path?
Determine the slack for each task. Show your work below. Enter your answer in the table above.