Consider the project activities given below: Optimistic Most Activity Predecessor Likely Pessimistic 12 13 10 10 13 10 10 10 B, D E, F where the appropriate managers have made estimates of the optimistic, most likely, and pessimistic times (in days) for completion of the activities a Draw the project network using activity on node (AON) dentify the critical activities?
https://media.cheggcdn.com/media%2Fed6%2Fed6b0c74-b3bb-49a6-8f4a-088435f8f684%2Fimage
Expert Answer
https://d2vlcm61l7u1fs.cloudfront.net/media%2Fa3e%2Fa3e162b6-78b3-4a14-afb5-3bbf20b2232f%2Fphp869tQL.png
https://d2vlcm61l7u1fs.cloudfront.net/media%2F0b7%2F0b719d8e-c545-48cb-8ed1-6cc60dfd107e%2FphpWhYXXq.png
B) critical activities are:
A-D-F-G