Consider the following information on job times and due dates (in hours).
Job
Job Time
Due Date
A
3.50
6.00
B
2.50
5.00
C
5.50
16.00
D
4.25
18.00
E
2.75
3.00
You are asked to determine the processing sequence using Shortest Processing Time (SPT) and Earliest Due Date (EDD) rule; and to decide which sequence is better for average job flow time and the average job tardiness performance measures.
FORMAT FOR ENTRIES:
• Sequence should be entered in the following format: D-E-B-C-A (with no spaces)
• Values for performance measures will be entered with two decimals after dot (5.00)
Enter the sequence using SPT rule: _________
For SPT sequence,