Case No. 53 ACCORD AND SATISFACTION Horn Waterproofing Court of Appeals 66 N.Y.2d 321; 497 N.Y.S.2d 310 (1985) FACTS: Plaintiff Horn Waterproofing Corp. (Horn) was hired by defendant Bushwick Iron and Steel Co., Inc. (Bushwick) to repair a leaking roof on a building owned by Rushwick. Horn worked on the roof for two days and then determined that, rather than a new roof was required. Horn billed Bushwick for $1080.00 for the two days of work. ick, disputing the amount of the bill, sent Hom a check for S500.00 and wrote the Bushw following on the back of it: “This