A project involving the installation of a new computer system into the emergency department comprises eight activities. The following table lists immediate predecessors and activity times (in weeks). What is the critical path?
Activity Predecessor Time
A – 5
B – 6
C A 2
D B,C 5
E D 4
F E 3
G B,C 9
H F,G 3