A project has 40 activities At the end of period 11, activity B is 75% completed. activity C is 90% completed, activity D is 100% completed, and activity E is 45% completed. The total budgeted costs activities B, C, D, and E are $40,000; $90,000; $70,000; and $80,000; respectively According to the project plan, the project cumulative budgeted cost at the end of period 11 is $201,000 and the total project budgeted cost is $3,000,000. The project cumulative actual cost at the end of period 11 is reported to be $250,000 NOTE: Do not use any comma in your answer