A large building company determined the need for cranes at three different building sites (A, B, and C) for the next 6 weeks (see Table 1). The demand for cranes is for full-time availability during a particular week. At the moment (start of week 0), all the cranes are located at the company’s main depot.
Site
Week 1
Week 2
Week 3
Week 4
Week 5
Week 6
A
1
2
1
0
0
0
B
0
1
2
2
1
1
C
1
0
0
0
2
2
Table 1: Demand for cranes at different locations
The time required to transport a crane between sites B and C is 2 weeks, while the transportation time between any other pair of locations (including the main depot) is only 1 week.