a. Create a Network Diagram b. Calculate ES, EF, LS, LF (Early Start, Early Finish, Late Start, Late Finish) c. Define the Critical Path d. How many weeks will the project take to complete? Immediate Weeks Predecessor 1.Activity
Expert Answer
https://d2vlcm61l7u1fs.cloudfront.net/media%2Fe51%2Fe5108f0d-f53c-4c65-b2e7-9da0dc092d0b%2FphpOOetbA.png
b) Early start of A = 0
Early finish of A = early start + activity time
Early finish of A = 0 + 8 ( 8 weeks)
early start of B = 0
early finish of B = 0 + 8 ( 8 weeks)
early start of C = early finish of A (8 weeks)
early finish of C = 8 + 9 (