Course Solutions Uncategorized (Answered) : a contractor repair works if building oprates 52 weeks a year uses continues review system for speacial paint . the follwoing da

(Answered) : a contractor repair works if building oprates 52 weeks a year uses continues review system for speacial paint . the follwoing da

a contractor repair works if building oprates 52 weeks a year uses continues review system for speacial paint . the follwoing data as below ,

demand : 90 bag / week

ordering cost = $ 54 per order

holding cost = 27 % of unit cost

lead time = 3 weeks

cycle service level = 80 %

standard divation of weekly demand =15 bags

on hand inventory =320 bags

find the below :

1- EOQ of this SKU

2- the avarage time between orders

3- Saftey sock

4- the Reorder point

5-an inventiery withdrawl of 10 bags was just made. is it time to reorder .

6- what will be the implication if the