7. A house building project consists of the following major activities. The activities and their major immediate predecessors are given below along with the time of completion.
a) Develop the project network diagram (5)
b) Show the various paths that lead from start to finish (Show each path) (3)
c) Which is the critical path? And why you call it critical path? (2)