2. Consider the following 5-job 4-machine flowshop makespan minimization problem in which all jobs and machines are available at time zero and the flow of jobs is from machine 1 through machine 4 Job MachineMachine 2 Machine 3Machine 4 18 14 25 29 28 23 25 26 25 16 1/2 (a) What is the number of all possible schedules? (b) What is the number of all possible permutation-type schedules? (c) Among all possible schedules, how many of them are enough to consider Now, consider the permutation-type schedules, answer the followings (d) Using the CDS algorithm, determine a feasible schedule and