11) (2 points) T/F The term “dummy activity” is a misnomer since each dummy represents work, takes time, and requires use of resources. 12) (2 points) T/F Redundant activities are activities that are repetitive of others and can be deleted from the project. 13) (2 points) T/F There can only be one critical path in a network. 14) (2 points) T/F If an activity has multiple predecessors, its late start is determined by the latest finish of its predecessors 15) (2 points) The latest allowable finish time that an event can occur, LF, depends on: (a) the earliest possible start