(10 points) For the information below, identify the critical path and the expected project duration. You need to show the flow map and work Activity Start Next A,B,C Duration 4 6 8 G,1 End End 3
https://media.cheggcdn.com/media%2F5fe%2F5fe7d438-0174-4edd-a9c8-348da223f5f9%2Fimage
Expert Answer
https://d2vlcm61l7u1fs.cloudfront.net/media%2F867%2F8675fb01-8a56-4c1f-bcf0-963925829b93%2Fphpfkdktc.png
Computation of earliest starting and finishing times is aided by two simple rules:
1. The earliest finish time for any activity is equal to its earliest start time plus its expected
duration, t:
EF = ES + t
2. ES for activities at nodes with one entering arrow is equal to EF of the entering arrow. ES
for activities leaving nodes with multiple entering arrows is
OR