ActivityABCDEFGHIJKLMweekly Pessimistic Time106126232812261268Weekly Most Likely Time2846322286227Weekly Optimistic Time243212166201034Immediate Successor_AACC-B, C, DEEFE, G, HJK
Required
1. Using Expected Time find out critical Path
2. What is Expected Start, Expected Finish, Latest Start, LatestFinish for each Activity
3. What is the slack Time of activity E, H, J, K and M
4. What the variance along Critical Path?
Expert Answer
Expected time = optimistic time + 4 x Most likely time +pessimistic time /6
Variance = [ pessimistic time – optimistic time/6]2
ActivityTPTmToTesigma^2A10223.3333331.777778B68470.111111C12435.1666672.25D6625.3333330.444444E2312.50.027778F3222.1666670.027778G2211.8333330.027778H8263.6666670.111111I12868.3333331J2662011.666671K1221050.111111L6232.8333330.25M8746.6666670.444444
Ans 1
Critical path is ACEHKM with a duration of 26.31
Ans 4 Variance of critical path is 4.713
Ans 2
ActivityESEFLSLFSlackA03.3303.330B3.3310.335.8212.822.49C3.338.493.338.490D8.4913.829.4912.821E8.4910.998.4910.990F02.169.6611.829.66G13.8215.6512.8214.651H10.9914.6510.9914.650I10.9919.3217.9826.316.99J2.1613.8211.8223.489.66K14.6519.6514.6519.650L13.8216.6523.4826.319.66M19.6526.3119.6526.310