Consider the following task set. Task CT T1 35 75 T2 10 40 T3 5 20 a) Verify whether the task set is schedulable under RM usi

Consider the following task set. Task CT T1 35 75 T2 10 40 T3 5 20 a) Verify whether the task set is schedulable under RM using the processor utilization-based approach b) Verify whether the task set is schedulable under RM using the response-time analysis approach c) Using a timeline, construct the RM schedule. d) Verify whether the task set is schedulable under EDF. e) Using a timeline, construct the