Course Solutions Uncategorized (Answered) : In the Pert, what happens to the probability of project completion when the variability goes up or down?

(Answered) : In the Pert, what happens to the probability of project completion when the variability goes up or down?

In the Pert,

what happens to the probability of project completion when the variability goes up or down?

Expert Answer


The probability of project completion is computed using z value table and calculating z value as below:
https://d2vlcm61l7u1fs.cloudfront.net/media%2F29a%2F29a33f80-ea0b-41f4-b685-09777dd01573%2FphpAyzTK4.png
Hence, when the standard deviation goes up, the z value will decrease and so the probability of project completion on specified time will decrease.

Similarly, when standard deviation goes down, z value will increase and thus the probability of project completion on specified time will increase.