Question 8 Suppose you are constructing either a mean chart with known variation or a p-chart to monitor some process. The process will only be stopped if a sample taken falls outside your control limits. If the process is in control, management wants only 12.6% of the samples taken to fall outside of your limits. (The company does not like stopping the process “accidentally”) What Z value should you use for your chart? 3.0 1.96 2.75 1.53 1.15