Consider the tasks, durations (in weeks), and predecessor relationships in the following network.
TIME
Earliest
Earliest
Latest
Latest
Activity
Predecessor
Optimistic
Most Likely
Pessimistic
Expected
Var
Start
Finish
Start
Finish
Slack
A
–
5
6
7
B
–
8
8
11
C
A
6
8
16
D
–
9
12
15
E
C
5
6
13
F
D
5
6
7
G
F
2
3
7
H
B
4
4
5
I
H
5
7
8
J
E,G,I
2
3
4
Compute the expected times
Compute the activity variances
Draw the network
Compute the ES and EF
Determine the expected completion time
Compute the LF ands LS
Compute the activity slacks
Determine the critical path
What is the probability of completing on or before week 22? After week 26?
What week would you only have a 30% chance of completing by?
Expert Answer
Solution :
Compute the expected times, Compute the activity variances, Draw the network, Compute the ES and EF, Compute the LF ands LS,Compute the activity slacks, What is the probability of completing on or