The activities described by the following table are given for the Howard Construction Project to remodel an existing facility. All times are in weeks.
Activity Immediate Predecessor(s) Duration
A NONE 9
B A 7
C A 3
D B 6
E B 9
F C 4
G E,F 6
H D 5
I G,H 3
A. Create aon pert diagram for Howard Construction’s project.
B. Using ES, EF and LS, LF methodology, determine and identify the crtical path.
C What’s the completion time on this project?
D. How much total slack there on noncritical paths?