Group of employees that work mon- Friday are working on a project that is scheduled to be done in 16 weeks.
Draw network diagram for the project
State what activities are critical to the project and what makes them critical
State non-critical paths and describe what non critical is
State the laterst start for activitity P, the earliest start for P and is there a slack.
State the expected duration
Should a manager be concerned about the project that is undergoing
Incase there is a $100 penalty for working day the project is late
Will the project cost late penalty and if it will, state how much