Which one of the following is true in MRP?
a. Safety lead time is used to handle uncertainty with demand
b. Safety stock works the same way as safety lead time
c. Safety lead is essentially inflated lead time
d. Two weeks of lead time plus one week of safely lead time equals three weeks of lead time
e. None of the above
Expert Answer
Safety lead time is basically to handle uncertainty of lead time and not demand. For uncertainty of demand, there is safety stock. So option a is not the answer.
Safety stock and safety lead time are altogether different concepts. So