Course Solutions Uncategorized (Answered) : The predecessor information and activity time estimates in months are as follows: Activity Immediate Predecessor Optimistic T

(Answered) : The predecessor information and activity time estimates in months are as follows: Activity Immediate Predecessor Optimistic T

The predecessor information and activity time estimates in months are as follows:

Activity Immediate Predecessor Optimistic Time Most likely Pessimistic Time Expected Time Variance

A None 2 4 6

B None 1 4 7

C A 2 2 2

D B 1 7 10

E D 2 4 6

F E 1 2 3

G C 3 4 17

H E, G 3 7 11

I E 8 9 10

J F, H 4 5 6

K I 1 1 1

Which of the following is the critical path?

ACGHJ

BDEHJ

BDEFJ

Expert Answer


Solution :

Critical Path : BDEHJ

https://d2vlcm61l7u1fs.cloudfront.net/media%2Fac2%2Fac2bb93b-da52-4de9-a800-a86ddc1eacc1%2Fphp6MJBT1.png

Leave a Reply

Your email address will not be published. Required fields are marked *

Related Post