2) In this simplified network schedule, tasks A, D, E, and F are the critical path. Based on this information, select the correct statement.
(IMAGE DESCRIPTION: Network diagram displays 6 tasks. Task A is at the start with zero float and it is a predecessor for tasks D and B. Task D has zero float and is a predecessor for tasks E and C. Task C has 6 days of float and is a predecessor for task F. Task E has zero float and is also a predecessor for task F. Task B has 6 days of float and is a