Table 2: Project Deliverables/Activities and Durations
Deliverable/Activity
Duration
Supplier Product Agreement
Sourcing Requirements
Develop sourcing team
3 days
Determine sourcing strategy
3 days
Sourcing Proposal
Assess the supply market
7 days
Analyze price and cost
7 days
Supplier Selection Criteria
Determine supplier ability to meet product and service quality
7 days
Identify any risk associated with supplier
7 days
Supplier Responsibility Standards
Implement management systems to ensure business continuity and continuous improvement
21 days
Monitor activities of a supplier to confirm compliance
30 days
Supplier Performance Measurement Criteria
Establish metrics & KPI for potential contacts
14 days
Evaluate and measure supplier performance through scorecards
30 days
Gantt Chart
Assume that the project starts on 10/30/2017. Using the data in Table 2 above, construct a Gantt Chart for the SCM project.