Course Solutions Uncategorized (Answered) : resource/tomterwa/sample %20wdInns%2020 pot No res Options ﹀ 7. Estimating Capacity Requirements Sure-foot Sandal Company operat

(Answered) : resource/tomterwa/sample %20wdInns%2020 pot No res Options ﹀ 7. Estimating Capacity Requirements Sure-foot Sandal Company operat

resource/tomterwa/sample %20wdInns%2020 pot No res Options ﹀ 7. Estimating Capacity Requirements Sure-foot Sandal Company operates two 8-hour shifts, five days per week, 50 weeks per year. A capacity cushion of 5 percent will suffice Time standards, lot sizes, and demand forecasts are: Time Standards Processi Setup Demand Forecast (pairslyr) 80,000 60,000 Lot Size Product (hr/lot)(pairs/lo) Men’s sandals Women’s sandals Children’s sandals ng (hr/pair) 0.05 0.10 0.02 0.5 2.2 3.8 240 180 360 120,000 Estimate Capacity Requirements: 8. A. Complete the following MPS for Product X 6 7 8 9

Expert Answer


Shifts/Day = 2

Hours/shift=8

Days/week =5
weeks/year =50

Cushion =5%

Productive hours =(2*8*5*50)*0.95

OR