Course Solutions Uncategorized (Answered) : Question 44 (4.5 points) An activity on a PERT network has these time estimates: optimistic 2, most likely- 3, and pessimistic-8.

(Answered) : Question 44 (4.5 points) An activity on a PERT network has these time estimates: optimistic 2, most likely- 3, and pessimistic-8.

Question 44 (4.5 points) An activity on a PERT network has these time estimates: optimistic 2, most likely- 3, and pessimistic-8. Its expected time and variance (if is a critical activity) are 1) none of these 2) 3.67;6 。3) 3.67; 1 4) 4.33:6 5) 4.33; 1 Save Question 45 (4.5 points) A project being analyzed by PERT has 38 activities, 16 of which are on the critical path. If the estimated time along the crtical path is 90 days with a project variance of 25, the 0.3446 2) 0.6554 3) 18 4) 0.0228 5) 0.9772

Expert Answer


44. 3.

OR

PayPal Gateway not configured

OR

PayPal Gateway not configured

Leave a Reply

Your email address will not be published. Required fields are marked *

Related Post

(Solved) : Assignment Shall Write Java Program Expects One Command Line Argument Indicating Path Vali Q38072830 . . . .(Solved) : Assignment Shall Write Java Program Expects One Command Line Argument Indicating Path Vali Q38072830 . . . .

<p><img alt="Assignment You shall write a Java program that expects one command-line argument indicating the path to a valid JFIF file con" src="https://media.cheggcdn.com/media%2F30a%2F30ab43f2-2089-4c9a-8dd1-32b489199322%2Fphpa5mlpf.png" style="height:502px;width:917px;" aria-describedby="d3f"/><img alt="Here is some code to