Course Solutions Uncategorized Four Stage Process One Worker Assigned Stage Activity Time Minute Unit Stage Activity Time Q34291376

Four Stage Process One Worker Assigned Stage Activity Time Minute Unit Stage Activity Time Q34291376

Four stage process

One worker is assigned to each stage. The activity time (in[minute/unit]) for each stage is:

Activity time per unit (sec)

A : 3

B ; 2.5

C: 4

D: 1.5

(a) Which stage is the bottleneck? What is the process capacityin [units/min]?

(b) Suppose the steps in activity C are made easier, so theactivity time per unit in step D is reduced by 60% (to 1.6[min/unit]). By how much does the capacity of the entire processincrease in [units/min]?

Expert Answer


a) Bottleneck activity is one with highest activity time = C

The capacity of process will be same as capacity of bottleneckactivity = 60/Activity time of C

OR

PayPal Gateway not configured

OR

PayPal Gateway not configured

Leave a Reply

Your email address will not be published. Required fields are marked *

Related Post

(Solved) : Day Centerlat Centerlon Fcount2015 04 10 427 738 12015 04 21 427 738 192015 05 10 427 738 Q32989512 . . . .(Solved) : Day Centerlat Centerlon Fcount2015 04 10 427 738 12015 04 21 427 738 192015 05 10 427 738 Q32989512 . . . .

DAY,CENTERLAT,CENTERLON,FCOUNT2015-04-10,42.7,-73.8,12015-04-21,42.7,-73.8,192015-05-10,42.7,-73.8,12015-05-27,42.7,-73.8,72015-05-30,42.7,-73.8,72015-06-09,42.7,-73.8,992015-06-12,42.7,-73.8,342015-06-13,42.7,-73.8,2762015-06-23,42.7,-73.8,52015-07-19,42.7,-73.8,1102015-08-03,42.7,-73.8,622015-08-04,42.7,-73.8,32015-08-11,42.7,-73.8,32015-08-15,42.7,-73.8,452015-09-03,42.7,-73.8,102<p><strong>PLEASE USE PYTHON</strong></p><p><strong>Lists and Files</strong></p><p>I have gathered together some interesting data into a filecalled UAlbanyLightning.txt</p><p>The file contains all recorded lightning strikes in the UAlbanyarea</p><p><strong>Parsing</strong></p><p>Review alist =str.split()            # alist will contain the