As part of a major plant renovation project, the industrialengineering department has been asked to balance a revised assemblyoperation to achieve an output of 240 units per eight-hour day.Task times and precedence relationships are as follows:
Task (A, B, C, D, E, F, G)
Duration (minutes 0.3, 0.5, 0.3, 0.5, 1.2, 0.8, 1.5)
Immediate Predecessor ( -, A, B, -, D, C, E,F)
Do each of the following:
a.Draw the precedence diagram.
b.Determine the minimum cycle time,the maximum cycle time, and the calculated cycle time.
c.Determine the minimum number ofstations needed.
d.Assign tasks to workstations on thebasis of most following tasks. Use shortest processing